2024 Winter Semester Flying Robot Project Team A Article 2November 20, 2024

620

This time, we worked on assembling the tail unit using the full-scale design plans we had printed during the previous session. To protect the blueprint, we covered it with plastic wrap and carefully placed the wooden parts on top, aligning them with the design. Using instant adhesive, we assembled the components piece by piece. Additionally, we inserted triangular reinforcements into the corners to enhance the structural strength.
At the same time, we have been progressing with the design of the main wing’s spar structure. Our aim is to start constructing the main wing next week. To achieve this, we need to finalize the rib structure and reevaluate the spar alignment from a strength perspective to ensure durability.
今回は以前の作業時に印刷した原寸大の設計図を用いて尾翼の組み立てを行いました。紙を傷つけないように張ったラップの上に、設計図に合わせて木材を置き瞬間接着剤で組み立てていきました。隅に三角形の補強材をはめ込むことで構造の強度を高めています。
それと同時に主翼の桁の構造の設計を進めており、来週には主翼の製作を始めたいです。そのためにはリブの構造を決定し桁の通し方を強度の観点から見直す必要があります。

|