2015 summer semester team D 7thJuly 01, 2015

620

We have managed to unite the left and right main wings, stretch a string amongst the main wing
in order to ensure rigidity and cover the main wing with strings of films.
Also, we were able to cut out the tires and obtain the mounting structure for electrical equipment.
Even though we had achieved our weekly milestones, we have yet to fix the main wing, tail assembly,
and other equipment on to the right positions of the body. Moreover, it came to us that we will
have to consider a measure to provide us with desorption of the main wing for flexibility.
Since we aim to carry out our full-scale test on next Friday, we had made a consensus on
how we will devote our limited amount of resource in the upcoming two days and we called it a day.

Department of Mechanical Engineering
Yasuo Kabe
今週は左右の主翼を結合し、翼表面の膜及び剛性を確保するための糸を張ることができた。
また、車輪を切り出し、電装系をマウントするための構造を確保した。
このように、先週の時点で設定したマイルストーンを達成することに成功したものの、
主翼、尾翼、電装系等のシャフトに対する位置を固定するまでは至らなかった。
さらに、柔軟な調整を許す上で、主翼をシャフトから取り外し可能とする構造を検討する必要が生じた。
金曜に全機試験を実施するため、次の2日間に持てるリソースをいかに配分するか合意形成した上で解散した。

機械工学科
可部泰生

|